New U.S.-Mexico truck crossings coming 2026 to 2031, and when

Pharr-Reynosa's second span is open now. The World Trade Bridge expansion (2027 to mid-2028), Douglas commercial port (fall 2028), Otay Mesa East (late 2028, cars first) and Colombia's freight-only bridges (2028 to 2030, depending on the source) are next; Green Corridors is 2031; the rest are proposals without dates.
Share:
copied
Map of the U.S.-Mexico border marking new truck crossing projects: Otay Mesa East, CA late 2028; Douglas, AZ fall 2028; Sunland Park, NM and Del Rio, TX proposed; Puerto Verde, TX permitted, no date; four Laredo, TX projects 2028 to 2031; Pharr, TX open now; Brownsville, TX no trucks.

The story

Only one new U.S.-Mexico truck crossing capacity project is open today: the Pharr-Reynosa second span, which doubled that bridge's commercial capacity in the fall of 2026. The next ones with public dates are the Laredo World Trade Bridge expansion (construction January 2027 to mid-2028, per the City of Laredo), the new commercial port at Douglas, Arizona (construction through fall 2028, per GSA), Otay Mesa East near San Diego (late 2028 for cars, trucks in later phases, per SANDAG) and two freight-only bridges at Colombia, Nuevo León (2028 to 2030, depending on the source). The Green Corridors elevated freight guideway near Laredo is permitted but not expected before 2031. Everything else on Mexico's list is a proposal without a public date. Last updated October 27, 2026.

What did Mexico announce in October 2026?

On October 14, 2026, Mexico's foreign minister Roberto Velasco told the Senate that Mexico is pushing eight new crossing projects with the United States: Mesa de Otay II-Otay Mesa East, Agua Prieta II-Douglas II, Anapra-Sunland Park, Acuña-Del Río II, Puerto Verde, Green Corridors (an elevated freight crossing between Nuevo León and Texas), Nuevo Laredo IV-Laredo V, and Flor de Mayo. He said almost 85% of bilateral trade moves through 56 bridges and crossings, and that the plan also includes longer operating hours, joint cargo inspections, non-intrusive scanners and routing heavy trucks around border cities. He said the Reynosa-Pharr expansion gets a binational inauguration in November (El Informador, October 14, 2026).

Eleven crossing projects by status, October 27, 2026. Open now: Pharr-Reynosa second span. Dated: World Trade Bridge, Douglas port, Otay Mesa East, Colombia bridges, Green Corridors. No public date: Laredo 4/5, Puerto Verde, Anapra-Sunland Park, Acuña II-Del Río II, Flor de Mayo (no trucks).
The eight projects Mexico named on October 14, 2026, plus Pharr-Reynosa, the World Trade Bridge expansion and Colombia, by status as of October 27, 2026.

Below is where each one stands with its operating agency, as of October 27, 2026.

Which projects have real dates?

ProjectCrossing pairStatusTrucks?ExpectedSource (date)
Pharr-Reynosa second spanPharr, TX - Reynosa, TamaulipasOpen; the city planned phased truck operations from mid-September, and the second structure was reported open October 8, 2026Yes, four new commercial lanesRibbon cutting planned November 12, 2026 (as of September 3)Texas Border Business (Sep 3, 2026); RGV Business Journal (Oct 8, 2026)
World Trade Bridge expansionLaredo, TX - Nuevo Laredo, TamaulipasDraft environmental assessment published March 2026; in designYes, commercial-only bridgeConstruction January 2027 to end of June 2028TxDOT notice (Mar 18, 2026); City of Laredo via KGNS (Sep 4, 2025)
Douglas commercial land port of entryDouglas, AZ - Agua Prieta, SonoraUnder construction since August 2025Yes, dedicated commercial portConstruction through fall 2028GSA (Sep 5, 2025)
Otay Mesa East (Otay II)San Diego, CA - Tijuana, Baja CaliforniaUnder construction; notice to proceed November 2025Later phases; first phase is northbound passenger vehiclesLate 2028, conditioned on the shared dynamic-toll technologySANDAG via Uniradio Informa (Sep 25, 2026); Border Report (Nov 2025)
Two freight-only bridges at ColombiaColombia, Nuevo León - Laredo, TXPresidential permit June 2025; announced August 28, 2026Yes, freight onlyConstruction from May 2027; completion 2028 (Mexico News Daily), 2029 (Nuevo León) or end of 2030 (City of Laredo's 2025 schedule)HCN Times (Sep 8, 2026); Mexico News Daily (Aug 31, 2026); KGNS (Sep 4, 2025)
Green Corridors elevated guidewayNear Laredo, TX, downstream of the Colombia bridge - Monterrey areaPresidential permit June 9, 2025; prototypes and a two-mile test trackYes, automated freight shuttlesNot before 2031White House permit (Jun 9, 2025); Transport Topics (Nov 21, 2025); Mexico News Daily (Aug 31, 2026)
Laredo 4/5 bridgeLaredo, TX - Nuevo Laredo IVPresidential permit October 3, 2024 to Southwebb Bridge Company LLCPermit covers a vehicular and pedestrian crossing; truck use not statedNo public dateFederal Register (Oct 8, 2024)
Puerto Verde (Nava)Maverick County, TX - Nava/Piedras Negras, CoahuilaPresidential permit to Maverick County (2024) for a vehicle, pedestrian and rail crossingNot stated publiclyNo public opening dateMexico Industry (Jun 4, 2024)
Flor de MayoBrownsville, TX - Matamoros, TamaulipasPresidential permit June 2024 to Cameron CountyNo; four-lane passenger and pedestrian bridgeNo public dateRep. Vicente Gonzalez release; Cameron County RMA (Jun 2024)
Anapra-Sunland ParkSunland Park, NM - Anapra, ChihuahuaProposed; the mayor has said the city will update its environmental study and resubmit its presidential permit applicationNot stated in the cited reportNo public dateBorder Report (about October 2025)
Acuña II-Del Río IIDel Rio, TX - Ciudad Acuña, CoahuilaProposed; corridor study stageIntended to move trucks off the downtown bridgeNo public dateLocal reporting (Prism News, Vanguardia)

Source: Cargado analysis of the agency and press sources listed with each row.

Timeline 2025 to 2031 of U.S.-Mexico truck crossing projects: Pharr-Reynosa span open; World Trade Bridge mid-2028 (construction January 2027 to mid-2028); Douglas port fall 2028; Otay Mesa East late 2028, cars first; Colombia bridges 2028 to 2030 by source; Green Corridors not before 2031. Four projects have no date.
Expected dates for each project with a public schedule, as of October 27, 2026. Ranges where the sources disagree.

Pharr-Reynosa is open now

Pharr's second span adds four commercial lanes and, per the RGV Business Journal (October 8, 2026), has "doubled its capacity with the opening of a second structure," which the city calls a 100% increase in bridge capacity. Bridge director Luis Bazan told Texas Border Business on September 3 that trucks would start using the new span in mid-September, with two lanes for Mexico-bound trucks at first, with the full expanded crossing in use about six weeks later and a ribbon cutting on November 12. Confirm the November 12 date with the City of Pharr before planning around it. Details on the crossing are on the Pharr-Reynosa page.

Laredo gets no new bridge capacity before mid-2028

The World Trade Bridge project widens the existing bridge by two southbound lanes and adds a new eight-lane northbound span about 1,479 feet long, according to TxDOT's draft environmental assessment notice (posted March 18, 2026, comments closed April 21, 2026). The City of Laredo's bridge director presented a schedule of construction from January 2027 to the end of June 2028 at the September 2, 2025 council meeting (KGNS). Until then, Laredo's options are the World Trade Bridge and the Colombia Solidarity Bridge.

At Colombia, Nuevo León governor Samuel García announced on August 28, 2026 two bridges "dedicated exclusively to commercial freight," an estimated $200 million split between Texas and Nuevo León, with construction expected to begin in May 2027 and finish in 2029 (HCN Times). Mexico News Daily reported the same project with completion in 2028. The City of Laredo's own September 2025 schedule for the Colombia expansion was later: design April 2027 to July 2028, construction from May 2029, completion at the end of 2030. The U.S. presidential permit for the Colombia expansion was signed in June 2025. Published completion dates therefore run from 2028 to the end of 2030 depending on the source; watch for a reconciled binational schedule.

The Laredo 4/5 bridge (Nuevo Laredo IV on the Mexican side) holds a presidential permit dated October 3, 2024, issued to Southwebb Bridge Company LLC (Federal Register, October 8, 2024). No construction schedule has been published.

Green Corridors is different in kind: an elevated guideway carrying automated freight shuttles between inland terminals near Monterrey and north of Laredo, permitted by the White House on June 9, 2025, "just downstream from the Laredo-Colombia Solidarity International Bridge." In November 2025 CEO Mitch Carlson told Transport Topics the company was building prototypes and a two-mile test track due in August or September 2026, at a cost he put at around $10 billion. Mexico News Daily reported in August 2026 that the system is not expected until 2031.

Otay Mesa East in San Diego opens for cars first

SANDAG received its notice to proceed in November 2025, and its executive director expected the work to take about three years (Border Report, November 13, 2025). In September 2026 SANDAG told Uniradio Informa that operations should begin in late 2028 ("Finales del 28"), on condition that the binational dynamic-toll technology is approved by both countries, and that the first phase covers northbound private light vehicles, with commercial lanes added in later phases. Trucks should keep planning around Otay Mesa and Tecate through at least 2028.

Douglas, Arizona gets a dedicated commercial port in 2028

GSA broke ground on September 5, 2025 on a $328 million commercial land port of entry on 80 acres 4.5 miles west of the Raul Hector Castro crossing in downtown Douglas. CBP will move commercial inspections there. GSA expects construction activity to continue through fall 2028.

The rest are proposals

Puerto Verde holds a presidential permit issued to Maverick County for a vehicle, pedestrian and rail crossing between the Eagle Pass area and Nava, Coahuila, about 35 kilometers from the Piedras Negras-Eagle Pass crossing (Mexico Industry, June 2024); no opening date has been published. Flor de Mayo is a four-lane passenger and pedestrian bridge between north Brownsville and Matamoros, permitted in June 2024; it is not a truck crossing. Sunland Park has no U.S. permit; its mayor has said the city will update its environmental study and resubmit its application (Border Report). Acuña II-Del Río II is at the corridor-study stage.

What it means for brokers and shippers

  • Rio Grande Valley: Pharr has more lanes now, in time for produce season. Capacity is not volume: Pharr's own southbound truck count was down 13.1% in September 2026.
  • Laredo: plan on today's two bridges through mid-2028, then the widened World Trade Bridge. Colombia's freight-only bridges are reported for completion between 2028 and the end of 2030, depending on the source.
  • San Diego and Arizona: Otay Mesa East and the Douglas commercial port are both 2028 projects; neither helps truck capacity in 2027.
  • Also coming: the softer measures in Mexico's plan (longer hours, joint inspections, scanners, truck bypasses) can change crossing times before any new bridge opens.

Cargado is the marketplace for Mexico and Canada freight: brokers post loads and get market rates by crossing, carriers find cross-border loads, and shippers get rates for their lanes at cargado.com.

Sources

Share:
copied

Frequently asked questions

When does the Pharr bridge expansion open?

It is open. The city planned phased truck operations on the second span from mid-September 2026, and the RGV Business Journal reported on October 8, 2026 that the second structure doubled the bridge's capacity. A ribbon cutting was planned for November 12, 2026, per Texas Border Business; confirm with the City of Pharr.

Will the new Colombia bridges carry trucks?

Yes. Nuevo León describes them as two bridges dedicated exclusively to commercial freight, about $200 million split with Texas, with construction from May 2027 and completion in 2029. Mexico News Daily reported 2028, and the City of Laredo's September 2025 schedule ran later, to the end of 2030.

When will Otay Mesa East take commercial trucks?

Not in the first phase. SANDAG projects operations in late 2028, starting with northbound passenger vehicles and conditioned on the binational dynamic-toll technology. Commercial lanes come in later phases with no published date.

What is Green Corridors?

An elevated guideway for automated freight shuttles between inland terminals near Monterrey and Laredo, permitted by the White House on June 9, 2025 just downstream of the Colombia Solidarity Bridge. It is in prototype and test-track stage and is not expected before 2031.

When does the World Trade Bridge expansion finish?

The City of Laredo's schedule is construction from January 2027 to the end of June 2028. The project widens the existing bridge by two southbound lanes and adds a new eight-lane northbound span, per TxDOT's March 2026 draft environmental assessment notice.